LIFE BAUXAL II project
The Life Bauxal II project, which will allow the demonstration of Paval- Refinal – Bauxal has been divided into 13 actions: 1 of preparation, 9 of implementation and 3 actions related to monitoring of environmental impact, dissemination and project management.
The project will last 4 years, from 01 July 2018 to 30 June 2022.
Project development
During the development of the project, the partners of the consortium will fulfill the following tasks:
Definiton of the prototype location
October 2018
Kick off meeting
November 2018
Creation of the website of the project
December 2018
Drawing of the Refining prototype
March 2019
A constructin of refining prototype
April 2019
Update of the LIFE KPI webtool (progress)
December 2019
First tones of Refinal
March 2020
Half of project
June 2020
End of the Refining prototype construction
Compliance with the Refining prototype startup
December 2020
Report about the optimization of operational parameters for refining prototype
Technical report for refining step
December 2020
Thecnical report for agglomerating step
Bauxal Technical report
June 2021
Technical report for milling step
September 2021
500 tons of BAUXAL along the Project
200 tones of Bauxal based refractories along the project
December 2021
500 tons of Refinal
150 tons of EU-Refinal
June 2022
Business plan
Life Cycle Analysis
Compliance of environmental LIFE indicators
Layman Report
June 2022
Final of the project
June 2022
Update of the LIFE KPI Webtool (final)
September 2022